Add a percentage Mark-up for CPR COs based on cost

When entering a change order item instead of calculating the mark-up manually if we need to mark-up an existing item, can we add a place to put the mark-up percentage and have it calculate it for us?

  • Attach files
  • Admin
    David Holler
    Aug 12, 2026

    Here is a screen shot showing the options in the Prime Contract setup, under "Default CPR/CO markups". You can choose "Percentage of Cost Resources" or "Margin Percentage on Cost Resources".

  • Cali Huys DS Constructors, LLC
    Oct 20, 2025

    Hi Roni, you can actually do this through the prime contract info module. It is located within the "Project Information Linked To Prime Contract" tile under the "View Default Markups - CPRs and COs" link. Hope this helps