Add "Finish Date With COs" field from Prime Contract to available bookmarks in document templates.

We would like to be able to pull the "Finish Date with COs" field from the Prime Contract module into the Detail Report Templates as a bookmark. This is especially useful for us on our CO template as we would like to have an updated Finish date based on CO impact days.

  • Attach files
  • John Gallagher
    Apr 15, 2026

    1000000%. I would consider this to be necessary information; I would hope that when a change order actually modifies the schedule, that the Project Manager would note that in the body/text of the change order with the revised date, but every change order that I've used from other programs (Procore, PMWeb, Prolog, CMiC) as well as the standard AIA G701 change order has this field.